This project has been sitting in the corner for at least 4 months patiently waiting my attention
Too fuggin cold to work so decided it was time to fire up me welder along with grinder.
I was not happy with the way it was looking ( ugly TS down tube ) . What the heck there are plenty of TS frames out there
Fisrt up I cut out the complete down tube about 40 mm down from seat rails and 55mm above pivot point
Bent up 2 new rails allowing for a Rm 125 b air box ...... re- used old engine mounts - just put a cut thru the centre to close them up as I have used 19mm OD x 2mmm tube ....suzuki had 22 x 2
Still undecided if I should gusset my weld or brace it.
Engine cases are Ts 250 that have also had the Oldfart treatment ( more on that latter )